The quick answer
Concrete is bought by volume: cubic yards for ready-mix trucks, or bags for small jobs. A 10 × 10 ft slab at the standard 4 inches thick needs 33.3 cubic feet — that’s 1.24 cubic yards, or about 56 bags of 80 lb pre-mix before waste. The difference between those two buying routes is mostly job size: under roughly a cubic yard, bags are cheaper; above it, a truck wins on price and sanity.
Bag yields: the numbers that matter
| Bag size | Yield (mixed) | Bags per cubic yard | Bags per m³ |
|---|---|---|---|
| 80 lb (36 kg) | 0.60 cu ft | 45 | ≈ 59 |
| 60 lb (27 kg) | 0.45 cu ft | 60 | ≈ 79 |
| 40 lb (18 kg) | 0.30 cu ft | 90 | ≈ 118 |
Yields are the manufacturers’ standard figures for mixed, placed concrete. Always round bag counts up — a slab that runs short mid-pour leaves a cold joint and a visible line forever.
Thickness guide: how deep should it be?
| Project | Typical thickness | Notes |
|---|---|---|
| Patio / walkway | 4 in (10 cm) | Foot traffic only |
| Driveway (cars) | 4–5 in | 5 in over weak soil; add rebar or mesh |
| Driveway (trucks / RV) | 6 in | Higher-strength mix recommended |
| Garage / shed floor | 4–6 in | 6 in if vehicles or heavy kit live there |
| Footings | Per local code | Depth must reach below the frost line |
Common mistakes to avoid
- Forgetting the waste allowance. Uneven subgrade eats volume — a “4-inch” slab over bumpy ground averages 4.5 inches. 10% waste is standard for a reason; scratch-built forms on rough ground may need 15%.
- Ordering a truck for a bag-sized job — or bags for a truck job. Mixing 60 bags by hand is a full day of brutal work. The crossover is roughly 1 cubic yard: above it, ready-mix is usually cheaper and better mixed.
- Ignoring short-load fees. Ready-mix trucks carry 8–10 yards; small orders often carry a short-load surcharge. Ask before ordering 1.5 yards and being surprised.
- Measuring thickness in your head. The form boards define the pour. Check their height with a tape at several points before you calculate — the calculator can only be as honest as the forms.
Pro tips
- Post holes add up: a fence line of 12 holes at 12 in wide × 36 in deep is over half a yard of concrete. Use the column shape and the quantity field.
- Order the truck for the “with waste” figure and have a small overflow project ready — a pad for bins or a step — so any spare concrete isn’t wasted.
- Working in metres? Switch units above: 1 m³ = 1.31 cu yd, and bag counts are computed from the same yields.
The complete guide
How much does a yard of concrete weigh? Why do slabs crack, and what do the pros check before the truck arrives? The complete guide covers volumes, bags, trucks and the mistakes that ruin pours.
Frequently asked questions
How much concrete do I need for a 10×10 slab?
At the standard 4 inches thick: 10 × 10 × (4 ÷ 12) = 33.3 cubic feet = 1.24 cubic yards. With 10% waste, order about 1.36 yards, or roughly 62 × 80 lb bags if you’re mixing it yourself.
How many bags of concrete make a cubic yard?
It depends on bag size: about 45 bags of 80 lb, 60 bags of 60 lb, or 90 bags of 40 lb pre-mix yield one cubic yard (27 cu ft) of placed concrete. The calculator shows all three counts for your exact volume.
How thick should a concrete slab be?
4 inches covers patios, walkways and most shed floors. Driveways for cars want 4–5 inches; heavy vehicles 6 inches. When in doubt, go thicker — an extra inch of concrete is far cheaper than replacing a cracked slab.
Should I buy bags or order ready-mix?
Bags win below about 1 cubic yard and for sites a truck can’t reach. Above a yard, ready-mix is usually cheaper per volume, arrives consistently mixed, and saves hours of labour. Many suppliers charge a short-load fee under 3–4 yards — ask first.
Why does the calculator add waste?
Because real ground isn’t flat. Subgrade dips, form bowing and spillage typically consume 5–10% extra. Running short mid-pour is the one concrete mistake you can’t undo, so the allowance is on by default — set it to 0 if you’d rather see the bare volume.
How much does a cubic yard of concrete weigh?
About 4,000 lb (roughly 2 tons, or 2,400 kg per cubic metre). That’s why delivery trucks and ground preparation matter — and why a “small” 3-yard driveway pour is a 6-ton event.
Related tools
More converters and handy calculators:
